Subject:                          Project Update -  Release02_AccessToSQL

 

A summary of the progress achieved in the release

Dear [XXX],

Here is an update...

Summary for Release02_AccessToSQL - http://cow.sydney.ssw.com.au/exchange/jacklin/Inbox/Northwind/Release02_AccessToSQL

Incident ID

Priority

Status

Est Hrs

Act Hrs

From

Subject

ABC-DEF

10 3 Completed

08:30

04:30

Jack J. Lin www.ssw.com.au

Task 1 - Setup a copy of your live database

123-456

20 3 Completed

06:30

08:00

Jack J. Lin www.ssw.com.au

Task 2 - Make a plan

JFC-PLA

20 3 Completed

12:00

11:30

Jack J. Lin www.ssw.com.au

Task 3 - Re-link the test databases

AAA-DDD

30 3 Completed

10:00

09:00

Jack J. Lin www.ssw.com.au

Task 4 - Script database changes for live deployment

UAX-LLM

30 3 Completed

08:00

08:00

Jack J. Lin www.ssw.com.au

Task 5 - Configure the query timeout

QQS-DDS

30 3 Completed

07:30

07:45

Jack J. Lin www.ssw.com.au

Task 6 - (Optional) Check the performance of your forms

6D6-D6D

30 3 Completed

07:30

07:00

Jack J. Lin www.ssw.com.au

Task 7 - Check that the database is split

BBC-DDS

40 3 Completed

10:00

11:00

Jack J. Lin www.ssw.com.au

Task 8 - (Optional) Change DAO code to use ADODB

7D7-SSA

40 3 Completed

11:00

10:00

Jack J. Lin www.ssw.com.au

Task 9 - Document the database

AXX-SZX

40 3 Completed

12:00

13:00

Jack J. Lin www.ssw.com.au

Task 10 - Remove Access permissions

CDA-ACP

40 3 Completed

13:00

12:45

Jack J. Lin www.ssw.com.au

Task 11 - Identify database problems

64R-OPW

50 1 To Do

15:00

Jack J. Lin www.ssw.com.au

Task 12 - Fix database problems

GGG-DDD

50 1 To Do

10:00

Jack J. Lin www.ssw.com.au

Task 13 - Run the Upsizing Wizard

BNM-NBX

50 1 To Do

08:00

Jack J. Lin www.ssw.com.au

Task 14 - Fix issues in the upsized database

DDD-SSS

50 1 To Do

07:00

Jack J. Lin www.ssw.com.au

Task 15 - Re-link the databases

DBD-SSS

50 1 To Do

08:00

03:00

Jack J. Lin www.ssw.com.au

Project Management

00D-S9S

50 1 To Do

08:00

Jack J. Lin www.ssw.com.au

Testing

PPO-0PO

50 1 To Do

08:00

Jack J. Lin www.ssw.com.au

Fix from user testing

Total

160:00

105:30

56:00 (remaining incomplete)

 

----- Report Generation Time: 2 second(s)

----- Generated by SSW eXtreme Emails! Version 16.48
----- The Simplest Project Management System Available
----- www.ssw.com.au/eXtremeEmails/