Skip Navigation LinksHome > SSW Standards > Better Software Suggestions > SSW Microsoft Project Suggestions

  1. Column Mapping - These should be in the same order

    • These should be in the same order.
    • Add that dialog should be resizable.
    The work items should be in the same order.
    Figure: These should be in the same order
  2. Column Mapping – Show the missing ones too

    Unmapped items
    Figure: It would help if you show the ones that are unmapped too
  3. Column Mapping – Show just the TFS fields *IMPORTANT*

    Insert column error
    Figure: When you "Insert Column" it is horrible... The lists go on and on and on...
    Need an option - Insert TFS Column
    Figure: When adding a column, we need a new one "Insert TFS Column"
    Need an option - Edit TFS Column
    Figure: When editing a column we need a new one "TFS Columns"
  4. Project Professional - Help me see days in hours

    I would like:

    • to be able to hover and see it in hours
    • to right click and change the format from days to
    • to fix the below bug with 'Project Options' | 'Duration is entered in' | 'Hours'
    Seeing Days
    Figure: I changed the setting, so why am I seeing days?
    I want to see hours (like I am used to in TFS)
    Figure: I want to see hours (like I am used to in TFS)

Acknowledgements

Adam Cogan