Exercise – Click Click Scrum
This exercise uses the VS2010 planning poker deck of cards & TFS
Separate out these as Chance Cards
Figure: Chance cards
Separate out these as Point Cards
Figure: Point cards
Sprint Planning (What): 20 minutes
Sprint Planning (How): 20 minutes
Each Day: 10 minutes ( x 9 days = 90 minutes)
Review: 20 minutes
Retro: 20 minutes
Total for 1 complete Sprint: 170 minutes (~3 hours)
NOTE: It is OK to really code rather than use “Click-Click” development as long as TFS is updated.
The PO reviews the work of the team (Note: if all the work was “Click-Click” then review the TFS work items to check that they are entered OK).
Students and PO do a standard Scrum retro for the exercise.
Table Example - Impediment
| ∞ - Impediment |
| Draw a point card |
| Add the value to the remaining hours of a task |
| Record the impediment |
Table Example - DBA will not give access to the database:
| ? - Clarification |
| Draw a point card |
| Add a new task |
| Set the remaining hours of a task to the value |
Table Example - The error message should change from “User Error” to “The process could not be completed, please check the Url value provided for the web service and try again”:
| 0 - Bug |
| Draw a point card |
| Create a bug |
| Add a task to the bug |
| Set the remaining hours on the task to the value |
Table Example - One of the build scripts fails on the build server, but works on a local dev machine:
| 20 - Bubble |
| Draw a point card |
| Create a bubble |
| Add a task to the bubble |
| Halve the remaining hours on a task |
Table Example - The data access layer supports the validation framework so as that was already implemented the effort expected has decreased:
| 40 - Spike |
| Draw a point card |
| Create a new PBI |
| Set the PBI points to the value |
Table Example - The current implementation may not support real-time display of information with the performance expected by users – investigate:
| 100 - Task blowout |
| Double the remaining hours on a task |